SFcheck

Pre-Screening Checklist

MF/CM TEMP OFFICE/SALES TRAILER APPLICATION

Completed Date: 4/20/2014

Item Number / Checklist Item

Yes / No / Additional Comments

1.

Did you receive the Submittal Form?

       

2.

Did you check the Contractor Registration?

       

3.

Did you check the Authorized Signatures?

       

4.

Did you receive the Initial Deposit?

       

5.

Did you receive the Certified Main Contract?

       

6.

Did you receive the Building Application?

       

7.

Did you receive the Electrical Application?

       

8.

Did you receive the Engineering Application?

       

9.

Did you receive the Environmental Application?

       

10.

Did you receive the FB application?

       

11.

Did you receive the Plumbing Application?

       

12.

Did you receive Zoning Application?

       

13.

Did you receive the CAB Application?

       

14.

Did you receive the Landscape Plan?

       

15.

Did you receive the Plans?

       

16.

Did you receive the Tie-Down Plan?

       

17.

Did you receive the Survey/Site Plan?

       

18.

Did you receive the Department Of Community Affairs Approval?

       

19.

Did you receive the Architect/Engineer Seal?

       

 

 

 

Close Print